The usual way a relining order gets scheduled is to ask a supplier how long delivery takes, add a week for luck, and call the result a plan. That plan measures the wrong interval. The interval that decides whether the rebuild finishes on time is the one between the day the machine stops and the day it cuts metal again, and only one of the blocks inside it belongs to the supplier. The other three belong to you: the teardown, the bonding window, and the scraping and acceptance work that follows it. Plan forwards from a delivery figure and the arithmetic always looks comfortable, which is exactly why it fails.
Four blocks, four different owners
A relining order sits inside four time blocks. Each block has a different owner and each is estimated from a different kind of evidence. Mixing them into a single number is where schedules lose their meaning.
| Block | Whose clock it is | What happens inside it | Estimate it from |
|---|---|---|---|
| Order to dispatch | Supplier | Material at the ordered thickness and width, cutting to the strip list, packing | A date range written into the quotation, per line |
| Dispatch to goods received | Carrier, forwarder, customs | Transit, clearance, inland delivery, unpacking and checking | Your own record of the last two shipments on the same lane |
| Teardown to surfaces ready | Your workshop | Stripping the old lining, degreasing, discovering wear that was not in the plan | The hours your fitters actually logged on the previous rebuild |
| Bonding to restart | Your workshop | Cure per the adhesive datasheet, removing machining allowance, scraping to contact, geometry checks | The adhesive cure schedule plus your own scraping history |
Start at the restart date and subtract
Write the date the machine must be back in production at the top of the page. Subtract acceptance checks, then scraping, then cure, then teardown, then transit, then the dispatch window. What is left is the date the order has to be placed. Do this once on paper before requesting anything, because the subtraction is what tells you whether the job is a schedule or a wish.
If the remaining date is already in the past, the honest conclusion is that the schedule does not close. Something in the scope has to change: the restart date, the number of axes in the first pass, or the assumption that all the material arrives together. Adjusting the arithmetic instead of the scope is how a rebuild ends up with the machine open on the floor and the liner still in a carton.
Two blocks you can compress, two you cannot
- Compressible: transit, by paying for a faster lane when the value of the machine justifies it.
- Compressible: dispatch, by ordering stock widths instead of a cut list that has to queue behind other work.
- Not compressible: adhesive cure, because it follows the datasheet and not the schedule.
- Not compressible: scraping to a contact pattern, because it is measured work and stops when the pattern is right, not when the calendar says so.
Teardown sits in between. Extra fitters shorten it, but only while the wear found is no worse than the plan assumed. The first hour of stripping is therefore also a planning event, not just a mechanical one.
Order the whole job, not only the sheet
The liner is one line of the order. The bonding system, the scraping paste and the cleaning consumables usually come from the same supplier and can travel in the same dispatch, but only if they were asked for at the same time. Ordered a week later, they arrive after the liner and the job still cannot start. The bundled material list for a multi-machine rebuild is the same problem seen from the other end: one schedule, one list, one dispatch window.
What to fix in the quotation
- A dispatch window per line, stated as a date range, with the thickness and width that line assumes.
- Whether the quoted width is stock or cut, because a cut width adds a queue that a stock width does not have.
- Packing form, because a coil and a flat stack are handled differently at goods-in.
- Incoterm, because it decides where your transit block begins and where the supplier responsibility ends.
- The validity period of the quotation, so that a re-plan does not restart the commercial conversation.
When the dates do not close
There are three options and no fourth. Move the restart date and accept the production loss. Split the order so the first axis is fitted while the rest is in transit. Or reduce the scope of the first pass, restoring one machine instead of the whole group. State which one you are taking to the people who own the machine before the order is placed, not after. A split order needs its quantities worked out properly first, which is what the relining quantity calculator is for.
Keep the record that makes the next plan faster
Every rebuild produces the numbers the next one needs: hours actually spent on teardown, days actually spent on cure and scraping, transit actually taken on that lane. Written down, they replace the guesswork in the next plan. Left in someone's memory, they are lost by the following shutdown. The same discipline applies to what arrives on the pallet, which is why storage and incoming inspection belongs in the same routine: material that arrives unchecked cannot be counted as received.
Send the strip list together with the restart date and the number of machines, and the quotation can come back in the form this page describes: dispatch window, stock or cut width, packing and incoterm. Start with the Blue liner range, add the two part epoxy adhesive and Tuschierpaste to the same order, or send the drawing with the dates you are working to.
Note: This page describes a sequencing method, not any supplier's stated lead time. Ask each supplier for its own dispatch window in writing and plan from that figure. Dates and windows in the example table are planning categories, not promises.