A rebuild covering several machines is usually bought the way a single machine is bought: each machine is measured when it is stripped, and added to the order as it comes apart. That works until the fourth machine, when the workshop holds three part-used rolls in one thickness, none in another, and a gib strip measuring 96 mm against stock that comes in 100 mm. Bundling is the alternative — one material list for the whole rebuild, built before the first machine is stripped.
Start with a machine list, not a material list
The unit of a bundle is the machine, not the square metre. Write one line per axis per machine before any area is added up. A field that cannot be filled in yet is better left blank: an estimated line silently sets the thickness for every other machine in the group.
| Field | What to record | Why it decides the order |
|---|---|---|
| Machine and axis | Machine ID, axis, the face being lined | Keeps strips traceable once rolls are unwrapped on the floor |
| Faces per axis | How many faces are lined, and the width of each | Sets strip count; area alone hides a two-face axis |
| Finished liner length | Length per strip, travel plus clearance | Sets the cut length taken from each roll |
| Thickness | Nominal thickness required after machining | The grouping key for the whole bundle |
| Colour | The colour the workshop already uses for that thickness | Colour is an identifier, not a grade — see the Turcite B colour guide |
| Back-in-service week | The week the machine has to cut again | Sets the delivery staging, not the material |
Consolidate by thickness, not by machine
Standard thickness runs 0.8 mm to 3.2 mm on the Blue liner range and across the other colours. A multi-machine rebuild usually collapses onto two or three of those steps, because the machining allowance that sets thickness clusters within one workshop. Grouping by thickness is what turns five machine lists into one order with three lines.
- Round each machine to a standard thickness unless the machining allowance requires a custom one. A custom thickness bought for one axis becomes a single-use roll.
- Keep one thickness for the gib strips across the whole bundle where the geometry allows. Gibs use the least material and cause the most mid-rebuild shortfalls.
- Assign one colour per thickness and use it on every machine. Mixed colours at the same nominal thickness is the fastest way to bond the wrong strip.
- Never split one bonded face across two thicknesses to use up stock. The face is one surface; the liner has to be one thickness.
Per-machine areas still have to be worked out before consolidation — the quantity calculator guide covers that arithmetic.
Work back from the stock widths
Width is where a bundle gains or loses material. Stock is listed at 100, 200, 300 and 305 mm; the 305 mm width is available on Blue and Brick Red, while Green and Brown are listed to 300 mm. Reading face widths against that list before ordering is the difference between offcut and waste.
| Stock width | Fits | Typical role in a bundle |
|---|---|---|
| 100 mm | Narrow ways, gib strips, small slides | One roll covers the gib strips of every machine in the group |
| 200 mm | Medium ways, box way sides, most saddles | The width that usually carries the most strips |
| 300 mm | Main ways on larger machines | Full-width strips with little nesting left over |
| 305 mm | Main ways, drawings based on a 12-inch roll | Avoids trimming when the original drawing is imperial |
Nesting narrow strips side by side on a wider roll is only valid when cut direction and bonding side both allow it: a strip cut across the roll is not interchangeable with one cut along it. Where a face is wider than the widest stock, ask for a custom width instead of joining two strips across a working surface — see the dovetail and box way layout guide.
Sequence the deliveries to the rebuild order
A bundle quoted as one lot arrives as one shipment and one invoice, but the workshop consumes it machine by machine. If the machine stripped first is not the machine at the top of the pallet, the schedule slips for reasons unrelated to machining. Set the split from the back-in-service dates.
- Ship the first stripped machine as its own lot inside the same order, so work starts without unpacking the rest.
- Keep the two-part epoxy adhesive and finishing paste with the first lot; adhesive is consumed from the first bond onwards.
- Ask for a per-lot packing list so a partial arrival can be checked without opening every carton.
- Confirm in writing whether partial shipment is allowed before the order is placed. Asking after the deposit removes the option.
Label every roll to one machine
The packing list survives about a day on a workshop floor; the label on the roll is what the fitter reads. Machine ID, axis, thickness, width, cut length and which side is the bonding side is the minimum that prevents a roll being cut for the wrong saddle.
- Print machine ID and axis in the largest type, above the material description.
- Mark the bonding side on the roll end, not only on the packing list.
- Keep one spare length per thickness with the bundle; a second shipment for one strip costs more in freight and time than the strip itself.
What to check when the bundle lands
A bundle is checked per lot but signed for once. Count rolls against the per-lot packing list before signing, measure thickness with a micrometer at three points along the roll, and confirm the cut edges are square. The full incoming routine, including storage before the machine is ready, is in the storage and incoming inspection guide.
What to put in the bundle enquiry
| Enquiry field | What to send |
|---|---|
| Machine count and type | Number of machines, and lathe, mill, grinder or machining centre for each |
| Face list | Per axis: number of faces and the width of each |
| Thickness grouping | Thickness per machine, and which machines share it |
| Colour convention | The colour already used in the workshop for each thickness |
| Delivery staging | Which lot ships first, and the back-in-service date behind it |
| Label format | The machine ID format you want printed on each roll |
Questions that come up when bundling
Can one roll cover two machines? Yes, when both use the same thickness and colour and the combined cut length fits the roll. Ask for the cut to be made at supply with each piece labelled separately.
One lot or several? One lot reduces formats and shipments to clear, but puts every machine behind the slowest measurement. Machines with a firm restart date are better staged; machines still waiting for stripping can be added later without touching the rest.
What if a machine is delayed? Say so before the cut list is confirmed. Strips cut for one machine cannot be re-cut longer, and a cancelled machine strands that length. Widths and thicknesses move between machines; cut lengths do not.
Send the machine list, the face widths and the thickness for each axis, and we will return one bundle quotation with the cut layout shown per lot. Start from the contact page, or ask for the Green or Brick Red sheet if your workshop works to that colour.